PhaseTypical Planning RangeWhat Happens
Planning & Feasibility2–6 weeksProperty review, project goals, zoning considerations and preliminary budget
Design & Engineering2–5 monthsArchitectural design, revisions, structural and building-system coordination
Permits & ApprovalsVariesZoning compliance, building permit and any additional approvals
Site Preparation2–6 weeksDemolition, clearing, utility coordination and site preparation
Foundation & Structure2–4 monthsExcavation, foundation, framing, roofing and enclosure
Building Systems1–3 monthsHVAC, plumbing and electrical rough-ins
Interior & Exterior Finishes3–6+ monthsDrywall, millwork, flooring, tile, fixtures and exterior work
Inspections & HandoverSeveral weeksFinal inspections, deficiencies, testing and move-in preparation